PTC LINDERO ELECTRICAL INSTALLATION
City: Añelo
Duration: 360 days
Year: 2021 – 2022
Features:
The project consisted of the following tasks:
- Civil
works and generator installation
- Installation
of power and control cable conduits and wiring
- Expansion
and modification of the existing main power panel
- Conduits,
wiring, and connections for heater installation
- Concrete
slab and metal shed for the installation of the inflation station
- Conduits,
fiber optic blowing and connections
- Supply,
installation and commissioning of compact transformer substations
- Supply,
construction, testing and energization of a 13.2 kV Medium Voltage Power
Line